Across Rosemount-Apple Valley-Eagan Public Schools, 11 major construction projects are underway. Approved by voters in May 2023, these improvements reflect our community’s strong commitment to preparing for enrollment growth, addressing safety and security, and ensuring an equitable educational experience across the district.
Emerald Trail Elementary: On Track and On Time
Emerald Trail Elementary (#20) will welcome its first students this fall. Using the same floor plan as East Lake Elementary, the district saved on architectural and design costs, stretched bond funds, and accelerated the construction timeline.
This summer, the district is working closely with the city of Rosemount to develop a school traffic safety plan for the site. This includes a one-mile bus zone so students won’t have to cross Bonaire Path walking to school. The school property will also be seamlessly connected to the city’s trail system, allowing neighbors and adults to use the property for daily walking routines. The traffic plan also includes additional crosswalks and the creation of a school speed zone on Bonaire Path. Watch for more information in August.
Rosemount Middle School: A New Chapter Begins
Just a few miles away, the walls are going up at the future site of Rosemount Middle School. The building’s footprint is now visible on the land formerly owned by the University of Minnesota and UMore Park. Slated to open in Fall 2027, this new middle school will replace the district’s oldest school building, initially built in 1918.
Activity Centers: Expanding Recreation and Wellness
We have officially broken ground on new activity centers at Apple Valley and Eastview High Schools. Families and visitors should be aware that site access and parking will be limited during the coming months as crews work to bring these long-awaited facilities to life.
When completed, all four activity centers—one at each comprehensive high school—will greatly expand community recreational opportunities, increase gym availability, and provide much-needed indoor space for wellness activities, youth sports, and extracurriculars. These aren’t just school improvements—they’re community assets that will serve the broader public for decades.
Next up: Rosemount and Eagan High Schools
Looking ahead, Rosemount High School’s construction project has moved into the bid phase, marking an important step toward transforming and expanding the existing facility. Meanwhile, the Eagan High School Activity Center is currently in the design phase.
Projects are also underway at Falcon Ridge, Scott Highlands, and Valley Middle schools. At Thomas Lake Elementary, a new dedicated bus loop and expanded parking will improve traffic flow. Districtwide, additional security cameras are being installed to enhance visibility and monitoring at all sites.